Construction of new European Parliament Luxembourg
|
|
Project period: 2009-2015 |
| Contract work: |
|
- Services:
- Master planning of site equipment
- Presentation in phase plans
- Preparation of a construction logistics concept
|
| Specifics: |
- Implementation during ongoing Parliamentary business
- Only two possible access roads
- Inner city construction site
- Short shell construction period, few delivery options
|
|
top
|
| |
Elbphilharmonie (philharmonic hall), Hamburg
|
|
Project period: 2007-2010 |
| Contract work: |
|
- Building machinery and equipment:
- Delivery and assembly of 5 revolving tower cranes (HH up to 120m) incl. crane concept
- Delivery and assembly of 136 containers (office, crew accommodation)
-
Scaffolding and shuttering:
- Large delivery of different shuttering systems for foundation and bare brick work:
- Framax and Streif Light formwork, climbing formwork, Flexdeck and Skydeck floor formwork, round steel columns, column formwork, heavy-duty props, Layher stacking tower, sinking platforms, folding platforms, transfer platform
- Special shuttering
- Work and weather protection enclosure
Services:
|
| Specifics: |
- Confined site in Hamburg's harbor/warehouse district, little storage and delivery space
- Containers were integrated directly into the steel scaffolding supporting the facade of the hollowed warehouse, at seven and a half meters above the water for flood protection
- Supply of crane parts on pontoons along the river Elbe
|
|
top
|
| |
Kreuzbauten, Federal Ministry of Education and Research, Bonn
|
|
Project period:
2005-2009
|
| Contract work: |
|
- Building machinery and equipment:
- Delivery and assembly of site restroom facility and office containers
- Scaffolding and shuttering:
- Services:
- Supply logistics/waste management
- Instruction of parties involved in the construction process
- Transportation logistics (delivery, unloading, use of building elevator)
- Video surveillance
- Security service and key management
- Space management / cleaning and tidying
- Daily meetings
|
| Specifics: |
- Construction during ongoing ministry activities
- High security requirements
- Multiple changes to the whole site equipment area
- Separation of site and ministry traffic
- Only possible site road is the underground garage roof with a max. load of 16t
|
|
top
|
| |
NATO Airbase Ramstein
|
|
Project period: 2005-2007 |
| Contract work: |
|
- Services:
- Preparation of a master plan for the transfer to Frankfurt - Ramstein
- Central recording, coordination and handling of all transportation
- Introduction and implementation of a logistics concept
- Authorizsation concepts / space management
- Organizational project work (meetings, training/instruction and consulting)
- Planning and equipment of a central control station
- Development of standard forms
- Access logistics in close cooperation with the military escort service
|
| Specifics: |
- Stringent security requirements
- Delivery only with escort
- Complex decision-making gremiums
- Highly confined site
|
|
top
|
| |
Pier A-PLUS, Frankfurt Airport
|
|
Project period: 2008-2012 |
| Contract work: |
|
- Building machinery and equipment:
- Delivery, assembly and catering service for several container systems (approx. 400) for parties involved in the construction
- Electrical site equipment (approx. 12km of cable; 200 connection boxes/switchgear)
- Supply of scaffolding, site elevators and hoisting devices
- Services:
- General site equipment and logistics
- Preparation of the site infrastructure (site roads, site water, telecommunications, crossings, technical infrastructure)
- Logistics coordination and management (space management)
- Site protection and site access control
- Site cleaning and waste management
|
| Specifics: |
- Stringent security requirements at the airport
- Consideration of air traffic
- Other building projects in the immediate vicinity requiring synchronization of transportation
- Crew traffic on the site
|
|
top
|
| |
BMW factory, Leipzig
|
|
Project period: 2001-2005 |
| Contract work: |
|
- Building machinery and equipment:
- Delivery and assembly of container systems
- Services:
- Supply logistics
- Access control
- Transportation scheduling
- Basic infrastructure (site roads, storage and parking spaces, fire brigade, site radio system, signage, winter service)
- Storage space management (planning of SE space requirement, contracting and maintenance of waste management)
- Earth mass logistics
- Coordination with site fire brigade and site security service
|
| Specifics: |
- Delivery of ready-to-use container system used primarily as info center and catering facility
- Nine building projects on a 514-acre lot
- On average, up to 450 trucks per day
- Close cooperation with the site security service
|
|
top
|
| |
Emporio, Hamburg
|
|
Project period: 2009-2011 |
| Contract work: |
|
- Building machinery and equipment:
- Delivery and assembly of 30 x 10m and 50 x 6m containers incl. media connections
- Electrical construction site equipment with transformer stations
- Delivery and assembly of a 280 EC-H 12 Litronic, stand-alone
- Delivery and assembly of a MDT 222 and two MDT 162
- Services:
- Site logistics coordination
- Site traffic management
- Storage facility management
- Access control
- Surveillance
- Provision of elevator operators
- Supply and waste management
- Winter service
- Energy supply
|
| Specifics: |
- The new building is erected right next to the listed Unilever high-rise
- To ensure stability of the free-standing crane without the usual connection to a building, tower elements of different strength were combined to taper up
- Restricted site due to city center location
|
|
top
|
| |
koelnmesse, north exhibition hall construction, Cologne
|
|
Project period: 2004-2005 |
| Contract work: |
|
-
Building machinery and equipment:
- Delivery and assembly of 5 revolving tower cranes:
- 180 EC-H
- 180 EC-H Litronic
- 280 EC-H 12 Litronic
- 280 EC-H
- Provision of 2 mobile cranes (Fuchs 118m)
- Provision of 2 crawler cranes (HITACHI KH 125)
- Provision of 4 telescopic stackers (AVT 1330 SLT)
- Delivery and assembly of 260 containers
- Electrical site equipment
|
|
|
|
|
|
top
|
| |
MaxCologne, Cologne
|
|
Project period: 2010-2012 |
| Contract work: |
|
- Building machinery and equipment:
- Delivery and assembly of 3 revolving tower cranes: two LH 180 EC-H10li and one LH 280 EC-H12li
- Provision of containers (site restroom facility, storeroom and access containers)
- Electrical site equipment
- Scaffolding and shuttering:
- 200 square meters of StreifLight frame formwork
- Services:
- Security and health and safety coordination
- Site power
|
| Specifics: |
- For space reasons, LH 280 EC-H12li will be set up on the existing high-rise. Due to the proximity to Cologne-Bonn airport and a helicopter landing space at the exhibition center in Deutz, the crane site required approval under air traffic laws.
|
|
top
|
| |
Munich Airport satellite extension
|
|
Project period: 2008-2014 |
| Contract work: |
|
- Services:
- Construction logistics planning
- Planning phases 1 to 9 based on HOAI (fee structure for architects and engineers)
- Preparation of a comprehensive security concept
|
| Specifics: |
- Construction during ongoing operations
- Parallel planning of tunnel and preparatory work
- Strict security requirements
|
|
top
|
| |
Office and administration building of GNS, Essen
|
|
Project period: 2009-2011 |
| Contract work: |
|
- Building machinery and equipment:
- Delivery and assembly of three revolving tower cranes: two MDT 178 and one LH 140 EC-H li
- Delivery and assembly of a container system made up of around 20 modules
- Electrical site equipment
- Scaffolding and shuttering:
- 450 square meters of StreifLight frame formwork for the foundations
- 800 square meters of support shuttering and 1,080 square meters of steel formwork for the walls
- 4,000 square meters of quick ceiling formwork and 1,500 square meters of panel floor formwork
- Services:
- Security and health and safety coordination
- Access control
|
|
|
|
|
|
top
|
| |
Publishing house Süddeutscher Verlag, Munich
|
|
Project period: 2006-2008 |
| Contract work: |
|
- Building machinery and equipment:
- Delivery and assembly of 5 revolving tower cranes (HH 131.6m and 120.3m with building bracing)
- Delivery and assembly of 64 office containers
- 1 access container with barrier
- Electrical site equipment incl. container supply connections, lighting
- Scaffolding and shuttering:
- Delivery of formwork for approx. 125,000sqm of area to be lined
- Some 150 running meter of fall and weather protection elements for the high-rise
- Services:
- Access control
- Setup of a central control station
- Access management with scheduled deliveries and collections
- Building floor management
- Site supervision
- Health and safety
- Supply and waste management logistics
- Daily waste disposal and primary site cleaning
- Coordination of site elevator times and cranes
|
| Specifics: |
- Inner city site
- Up to 100 subcontractors on site at a time
- Two site access poin
- Highly confined site
|
|
top
|
| |
United Nations Campus (UNC), Bonn
|
|
Project period: 2009-2011 |
| Contract work: |
|
- Building machinery and equipment:
- Delivery of site power, lighting and water
- Delivery and assembly of 21 daytime accommodation and four sanitary containers
- Delivery and assembly of escape staircases and escape bridges
- Flood protection for the building right next to the Rhine
- Equipment of a first-aid facility
- Provision of chemical toilets
- Services:
- Traffic safety
- Management and control of staff and vehicle movements
- Access control and surveillance
- Transportation logistics and waste disposal management
- Demolition and dismantling for site clearance
- Delivery and setup of hoardings and gate systems
- Delivery and setup of a tire cleaning facility
- Commissioning of an existing elevator, and delivery and installation of a building elevator
- Dismantling and landscaping, setup of the site facility areas and site roads
- Cleaning services (outside, site management container and accommodations)
|
|
|
|
|
|
top
|
| |
University Hospital, 2nd construction phase, Giessen
|
|
Project period: 2009-2010 |
| Contract work: |
|
- Building machinery and equipment:
- Delivery and setup of 100 office and day accommodation containers
- Services:
- Transportation logistics
- Storage space management
- Traffic area management
- Subcontractor logistics coordination
- Site protection and surveillance incl. identification system
- Implementation of the fire protection concept
- Provision of elevator operators
- Supply and waste management logistics
- Provision of Dixi toilets
|
| Specifics: |
- At peak times, there are up to 500 people working on the site
- Coordination of an average 50 transportations/day
|
|
top
|
| |
Rheinau harbor, Cologne
|
|
Project period: 2001-2009 |
| Contract work: |
|
- Building machinery and equipment:
- Provision of cranes, electrical SE, containers for the individual projects
- Services:
- Logistics control / management of storages space
- Access control
- Coordination with all involved re. access, loading/unloading, storage space, etc.
- Instruction of parties involved in construction
- Security coordination
- Coordination of flood protection
- Power supply
|
| Specifics: |
- Total area covers a length of approx. 2km, some 30 building projects in the area, 3 entrances max.
- Compliance with preservation order
- Parallel events (sports, chocolate museum)
- Some site parts already occupied by users/lessees during construction
|
|
top
|
| |
ThyssenKrupp quarters, Essen
|
|
Project period: 2007-2010 |
| Contract work: |
|
- Building machinery and equipment:
- Delivery and assembly of containers for various parties involved in the construction
- Electrical site equipment
- Scaffolding and shuttering:
- 3,000sqm of frame shuttering
- 3,950sqm of panel floor formwork
- Services:
- Construction logistics master plan
- Access control
- Setup of a central logistics control station
- Safety and health protection coordination
- Coordination of construction logistics for interior works
- Planning and coordination of furniture logistics and moving logistics
- Traffic control to and on site
- Cleaning during occupation of the premises
- Power supply
|
| Specifics: |
- 568 acres of inner city site
- Invovelment of around twelve general contractors
- At times up to 100 companies working on site
- One site access point
|
|
top
|
| |
Tower 185, Frankfurt
|
|
Project period: 2009-2011 |
| Contract work: |
|
- Building machinery and equipment:
- Delivery and assembly of seven luffing jibs: three Wolffkran 355 B, three Wolffkran 180 B, one 160 HC-L
- Delivery and assembly of 70 office and daytime accommodation containers
- Supply, maintenance and servicing of all electrical site equipment
- Provision of site utilities
- Scaffolding and shuttering:
- System shuttering for straight walls and cores
- Flex ceiling shuttering
- Flexible circular shuttering elements for curved walls
- Bearer beams and shaft platforms
- Various support shutterings and door system recesses
- Proprietary StreifLight for parapets and walls to be erected later
- Use of hydraulic self-climbing formwork for core outer walls and perforated facade
- Services:
|
| Specifics: |
- Two Wolffkran 355 B will climb to a final height of 190m and will be anchored to the building using seven bracings
|
|
top
|
| |
Closing event of XXth World Youth Day 2005, Cologne
|
|
Project period: 2005 |
| Contract work: |
|
- Services:
- Organization of over 30 parking lots around Cologne
- Organization of pedestrian/vehicle movement during the closing event
- Provision of over 750 stewards and security staff
- Outside parking lot supervision
- Guidance and supervision of the outside parking lot
- Transfer logistics from parking lots to Marienfeld incl. pay point management
- Tidying and cleaning
- Blocking off and securing of shuttle stops
- Provision of pay booths (approx. 700) and security staff
- Provision of sanitary facilities/tidying and cleaning
- Preparation of project organization with task assignment/responsibilities
- Detailed exchange of information with traffic control center and the police authorities of the WYD with 24/7 availability
|
| Specifics: |
- High number of attendees (approx. 1.2m pilgrims)
- High volume of vehicles (approx. 7,000 buses and approx. 50,000 cars within 48 hours)
- Extremely short commissioning period (approx. 10 days)
- Some venues geographically far apart
|
|
top
|
| |
|
|
| References - Services |
|
BMW factory, Leipzig
|
|
Closing event of XXth World Youth Day 2005, Cologne
|
|
Construction of new European Parliament Luxembourg
|
|
Elbphilharmonie (philharmonic hall), Hamburg
|
|
Emporio, Hamburg
|
|
koelnmesse, north exhibition hall construction, Cologne
|
|
Kreuzbauten, Federal Ministry of Education and Research, Bonn
|
|
MaxCologne, Cologne
|
|
Munich Airport satellite extension
|
|
NATO Airbase Ramstein
|
|
Office and administration building of GNS, Essen
|
|
Pier A-PLUS, Frankfurt Airport
|
|
Publishing house Süddeutscher Verlag, Munich
|
|
Rheinau harbor, Cologne
|
|
ThyssenKrupp quarters, Essen
|
|
Tower 185, Frankfurt
|
|
United Nations Campus (UNC), Bonn
|
|
University Hospital, 2nd construction phase, Giessen
|
|