Projects

 

Airrail Center, Frankfurt

Project period: 2007-2010
Contract work:
  • Building machinery and equipment:
    • Delivery and assembly of 7 revolving tower cranes: three 280 EC-H, two MDT 222, one MDT 218 and one MDT 302
    • Maintenance and repair of all 17 RTCs used on the site
    • Provision of four transport elevators MX 2024
    • Delivery and assembly of 130 containers (site restroom facility, office and first aid containers)
    • Winter heating: delivery and installation of a heating system consisting of 81 devices with a heat output of 11,800KW incl. the required site power supply
Specifics:
  • Site located right next to Frankfurt Airport, above the long-distance railway station and between the heavily frequented highway A3 and freeway B43
  • All cranes were provided with obstruction lights due to their vicinity to Frankfurt Airport, and with work area boundaries due to their closeness to the highways.
 
top
 

Barwa Commercial Avenue, Qatar

Project period: 2008-2009
Contract work:
  • Scaffolding and shuttering:
    • Sale of a total approx. 5,000sqm of StreifLight (steel) and StreifTelos wall and pillar shuttering
    • 20,000sqm of beam and ceiling shuttering from our partner companies Faresin and Pafili
    • On-site services:
      • provision of topping-out foremen, coordination and supervision of initial assembly of the shuttering, staff training in formwork handling
Specifics:
  • Development of a shuttle carriage for propping platforms which allows whole components to be shifted
  • Development of a pre-assembled stair formwork system which allows stairs and landings to be pre-assembled in one piece on site
  • Transportation of approx. 2,000t of material in 100 maritime containers to Doha
 
top
 

BMW factory, Leipzig

Project period: 2001-2005
Contract work:
  • Building machinery and equipment:
    • Delivery and assembly of container systems
  • Services:
    • Supply logistics
    • Access control
    • Transportation scheduling
    • Basic infrastructure (site roads, storage and parking spaces, fire brigade, site radio system, signage, winter service)
    • Storage space management (planning of SE space requirement, contracting and maintenance of waste management)
    • Earth mass logistics
    • Coordination with site fire brigade and site security service
Specifics:
  • Delivery of ready-to-use container system used primarily as info center and catering facility
  • Nine building projects on a 514-acre lot
  • On average, up to 450 trucks per day
  • Close cooperation with the site security service
 
top
 

Cheves, Peru

Project period: 2010
Contract work:
  • Building machinery and equipment:
    • Delivery, assembly and equipment of containers as temporary facilities. 2 units Contractors Office of 639,26 m² and 1 Employers Office of 636,93 m².




 
 
top
 

Emporio, Hamburg

Project period: 2009-2011
Contract work:
  • Building machinery and equipment:
    • Delivery and assembly of 30 x 10m and 50 x 6m containers incl. media connections
    • Electrical construction site equipment with transformer stations
    • Delivery and assembly of a 280 EC-H 12 Litronic, stand-alone
    • Delivery and assembly of a MDT 222 and two MDT 162
  • Services:
    • Site logistics coordination
    • Site traffic management
    • Storage facility management
    • Access control
    • Surveillance
    • Provision of elevator operators
    • Supply and waste management
    • Winter service
    • Energy supply
Specifics:
  • The new building is erected right next to the listed Unilever high-rise
  • To ensure stability of the free-standing crane without the usual connection to a building, tower elements of different strength were combined to taper up
  • Restricted site due to city center location
 
top
 

Galeria Malta shopping and leisure center, Posen

Project period: 2007-2008
Contract work:
  • Building machinery and equipment:
    • Delivery, assembly and maintenance of 8 revolving tower cranes
 
 
top
 

Grand Mall, Varna

Project period: 2009-2010
Contract work:
  • Building machinery and equipment:
    • Delivery and assembly of 7 revolving tower cranes:
      • 1 71 EC,
      • 2 71 EC-B5
      • 4 180 EC-H
    • Two 120m elevators
 
 
top
 

koelnmesse, north exhibition hall construction, Cologne

Project period: 2004-2005
Contract work:
  • Building machinery and equipment:
    • Delivery and assembly of 5 revolving tower cranes:
      • 180 EC-H
      • 180 EC-H Litronic
      • 280 EC-H 12 Litronic
      • 280 EC-H
    • Provision of 2 mobile cranes (Fuchs 118m)
    • Provision of 2 crawler cranes (HITACHI KH 125)
    • Provision of 4 telescopic stackers (AVT 1330 SLT)
    • Delivery and assembly of 260 containers
    • Electrical site equipment
  • Services:
    • Energy supply
 
 
top
 

Landmark tower and base building, Bremen

Project period: 2009-2010
Contract work:
  • Scaffolding and shuttering:
    • Delivery of shuttering for walls, ceilings, columns and project-related climbing formwork for the elevator walls:
      • Framax frame shuttering
      • Streif round steel shuttering (support columns)
      • Streif-KS column formwork (for square columns)
      • Streif quick ceiling support formwork in connection with filigree support
      • ID15 heavy-duty tower for the foyer in connection with a quick ceiling support system
      • Skydeck with drophead system for the floor formwork
      • KG240 for the elevator walls on the outside of the tower (in combination with WWP)
    • 82 running meters of work and weather protection enclosure (WWP)
Specifics:
  • Due to highly acute-angled corners, special parts were added to the work and weather protection elements.
  • Client used the WWP for large-space advertising.
 
top
 

MaxCologne, Cologne

Project period: 2010-2012
Contract work:
  • Building machinery and equipment:
    • Delivery and assembly of 3 revolving tower cranes: two LH 180 EC-H10li and one LH 280 EC-H12li
    • Provision of containers (site restroom facility, storeroom and access containers)
    • Electrical site equipment
  • Scaffolding and shuttering:
    • 200 square meters of StreifLight frame formwork
  • Services:
    • Security and health and safety coordination
    • Site power
Specifics:
  • For space reasons, LH 280 EC-H12li will be set up on the existing high-rise. Due to the proximity to Cologne-Bonn airport and a helicopter landing space at the exhibition center in Deutz, the crane site required approval under air traffic laws.
 
top
 

Munich Airport satellite extension

Project period: 2008-2014
Contract work:
  • Services:
    • Construction logistics planning
    • Planning phases 1 to 9 based on HOAI (fee structure for architects and engineers)
    • Preparation of a comprehensive security concept
Specifics:
  • Construction during ongoing operations
  • Parallel planning of tunnel and preparatory work
  • Strict security requirements
 
top
 

North Gate Mall, Doha, Qatar

Project period: 2011-2014
Contract work:
  • Services:
    • Leasing of 8 tower cranes
    • Assembly and disassembly
    • Crane drivers
    • Crane service during the lease period
 
 
top
 

Office and administration building of GNS, Essen

Project period: 2009-2011
Contract work:
  • Building machinery and equipment:
    • Delivery and assembly of three revolving tower cranes: two MDT 178 and one LH 140 EC-H li
    • Delivery and assembly of a container system made up of around 20 modules
    • Electrical site equipment
  • Scaffolding and shuttering:
    • 450 square meters of StreifLight frame formwork for the foundations
    • 800 square meters of support shuttering and 1,080 square meters of steel formwork for the walls
    • 4,000 square meters of quick ceiling formwork and 1,500 square meters of panel floor formwork
  • Services:
    • Security and health and safety coordination
    • Access control
 
 
top
 

Petionville - Port-au-Prince, Haiti

Project period: 2011
Contract work:
  • Building machinery and equipment:
    • Delivery, assembly and equipment of containers as temporary facilities ready-for-use for the embassy of the Commission of the European Community
    • Logistical clearing of all material to the site in Petionville (i.e.: transport of all material to Antwerpen, water carriage to Port-au-Prince, temporary storage of containers at harbour and transport at countryside)
    • Technical add-ons e.g. pitch roof as steel building, a central air conditioning system as well as intensified safety arrangements
Specifics:
  • Due to the difficult situation in Haiti after the earthquake in 2010 a planning reliability was only achieved with maximum effort
  • At times, specific hourly scheduling of assembly and equipment work
  • Maximisation of assignment local resources
  • Stringent security requirements

 
top
 

Publishing house Süddeutscher Verlag, Munich

Project period: 2006-2008
Contract work:
  • Building machinery and equipment:
    • Delivery and assembly of 5 revolving tower cranes (HH 131.6m and 120.3m with building bracing)
    • Delivery and assembly of 64 office containers
    • 1 access container with barrier
    • Electrical site equipment incl. container supply connections, lighting
  • Scaffolding and shuttering:
    • Delivery of formwork for approx. 125,000sqm of area to be lined
    • Some 150 running meter of fall and weather protection elements for the high-rise
  • Services:
    • Access control
    • Setup of a central control station
    • Access management with scheduled deliveries and collections
    • Building floor management
    • Site supervision
    • Health and safety
    • Supply and waste management logistics
    • Daily waste disposal and primary site cleaning
    • Coordination of site elevator times and cranes
Specifics:
  • Inner city site
  • Up to 100 subcontractors on site at a time
  • Two site access poin
  • Highly confined site
 
top
 

Residential building, Moscow

Project period: 2010-2011
Contract work:
  • Building machinery and equipment:
    • Delivery and assembly of a revolving tower crane Liebherr 550 EC-H 40, set up as free-standing unit, with a hook clearance of 84m
Specifics:
  • The LH 550 EC-H 40 was one of the first Liebherr cranes of this type to be set up in Russia.






 
top
 

Rheinau harbor, Cologne

Project period: 2001-2009
Contract work:
  • Building machinery and equipment:
    • Provision of cranes, electrical SE, containers for the individual projects
  • Services:
    • Logistics control / management of storages space
    • Access control
    • Coordination with all involved re. access, loading/unloading, storage space, etc.
    • Instruction of parties involved in construction
    • Security coordination
    • Coordination of flood protection
    • Power supply
Specifics:
  • Total area covers a length of approx. 2km, some 30 building projects in the area, 3 entrances max.
  • Compliance with preservation order
  • Parallel events (sports, chocolate museum)
  • Some site parts already occupied by users/lessees during construction
 
top
 

Rondo 1 office building, Warsaw

Project period: 2003-2005
Contract work:
  • Building machinery and equipment:
    • Delivery, assembly and maintenance of 2 revolving tower cranes
Specifics:
  • The tallest crane climbed to over 200m
 
top
 

Schorsa residential complex, Kiev

Project period: 2007
Contract work:
  • Building machinery and equipment:
    • Delivery and assembly of 3 revolving tower cranes
 
 
top
 

Sheraton Car Park, Doha, Qatar

Project period: 2011-2012
Contract work:
  • Services:
    • Leasing of 2 tower cranes
    • Assembly and disassembly
    • Crane service during the lease period
 
 
top
 

SkyTower multifunctional complex, Breslau

Project period: 2008-2012
Contract work:
  • Building machinery and equipment:
    • Delivery, assembly and maintenance of 5 revolving tower cranes
Specifics:
The tallest crane climbed to 260m
 
top
 

Terminal 2 construction, Munich Airport

Project period: 2000-2001
Contract work:
  • Scaffolding and shuttering:
    • Delivery of formwork for carcass work (560,000sqm of area to be lined)
    • Technical job processing and preparation of timing and process plans
    • Share in joint supplies: 60%
    • Local formwork coordinators
 
 
top
 

ThyssenKrupp quarters, Essen

Project period: 2007-2010
Contract work:
  • Building machinery and equipment:
    • Delivery and assembly of containers for various parties involved in the construction
    • Electrical site equipment
  • Scaffolding and shuttering:
    • 3,000sqm of frame shuttering
    • 3,950sqm of panel floor formwork
  • Services:
    • Construction logistics master plan
    • Access control
    • Setup of a central logistics control station
    • Safety and health protection coordination
    • Coordination of construction logistics for interior works
    • Planning and coordination of furniture logistics and moving logistics
    • Traffic control to and on site
    • Cleaning during occupation of the premises
    • Power supply
Specifics:
  • 568 acres of inner city site
  • Invovelment of around twelve general contractors
  • At times up to 100 companies working on site
  • One site access point
 
top
 

Tower 185, Frankfurt

Project period: 2009-2011
Contract work:
  • Building machinery and equipment:
    • Delivery and assembly of seven luffing jibs: three Wolffkran 355 B, three Wolffkran 180 B, one 160 HC-L
    • Delivery and assembly of 70 office and daytime accommodation containers
    • Supply, maintenance and servicing of all electrical site equipment
    • Provision of site utilities
  • Scaffolding and shuttering:
    • System shuttering for straight walls and cores
    • Flex ceiling shuttering
    • Flexible circular shuttering elements for curved walls
    • Bearer beams and shaft platforms
    • Various support shutterings and door system recesses
    • Proprietary StreifLight for parapets and walls to be erected later
    • Use of hydraulic self-climbing formwork for core outer walls and perforated facade
  • Services:
    • Energy supply
Specifics:
  • Two Wolffkran 355 B will climb to a final height of 190m and will be anchored to the building using seven bracings
 
top
 

Vienna Skylink, Vienna

Project period: 2005-2009
Contract work:
  • Building machinery and equipment:
    • Delivery, assembly and management of three container villages (office, crew, sanitary containers):
      • 111 containers, 3-story
      • 90 containers, 3-story
      • 66 containers, 3-story
      • incl. all sideline work such as foundation work, water and waste water connection, disposal and separation of waste material, management of quarters, monitoring of house rules and daily cleaning
    • 20 storage containers
    • Delivery of 2 revolving tower cranes 180 EC-H
    • Electrical site equipment:
      • four transformer stations 1000V
      • almost 9km of cabling
      • over 100 switch cabinets
    • Telescopic stacker
Specifics:
  • Stringent security requirements at the airport
  • Relocation of the container villages during ongoing operations due to construction progress
  • Several modifications of electrical installations due to construction progress
 
top
 

Weser Tower, Bremen

Project period: 2008-2009
Contract work:
  • Building machinery and equipment:
    • Delivery and assembly of a Liebherr EC-H Litronic
  • Scaffolding and shuttering:
    • Delivery of shuttering for reinforced concrete works and formwork systems:
      • 350sqm of steel formwork
      • 500sqm of special shuttering for exposed concrete SB3
      • 1,500sqm of panel floor formwork
      • Square column formwork, round steel column systems, two crane displaceable climbing frame units with pertinent finishing platform
    • 110 running meters of work and weather protection enclosure
Specifics:
  • Crane of 98 meters was set up as free-standing unit
 
top
 

Zlote Tarasy multifunctional complex, Warsaw

Project period: 2003-2005
Contract work:
  • Building machinery and equipment:
    • Delivery, assembly and maintenance of 10 revolving tower cranes with different configurations
Specifics:
Back then, the site of the building complex was one of the biggest in Europe; to avoid a collision of cranes, all top slewing cranes were provided with a 'top tracing' system
 
top
 
References - Commercial buildings
Airrail Center, Frankfurt
Barwa Commercial Avenue, Qatar
BMW factory, Leipzig
Cheves, Peru
Emporio, Hamburg
Galeria Malta shopping and leisure center, Posen
Grand Mall, Varna
koelnmesse, north exhibition hall construction, Cologne
Landmark tower and base building, Bremen
MaxCologne, Cologne
Munich Airport satellite extension
North Gate Mall, Doha, Qatar
Office and administration building of GNS, Essen
Petionville - Port-au-Prince, Haiti
Publishing house Süddeutscher Verlag, Munich
Residential building, Moscow
Rheinau harbor, Cologne
Rondo 1 office building, Warsaw
Schorsa residential complex, Kiev
Sheraton Car Park, Doha, Qatar
SkyTower multifunctional complex, Breslau
Terminal 2 construction, Munich Airport
ThyssenKrupp quarters, Essen
Tower 185, Frankfurt
Vienna Skylink, Vienna
Weser Tower, Bremen
Zlote Tarasy multifunctional complex, Warsaw
back   top
STREIF Baulogistik | Copyright © 2009 STREIF Baulogistik